Project News

December 2024: The Limone hydroelectric power plant was successfully completed.

November 2024: See the current construction progress (as of November 14, 2024). The turbines have been installed.

September 2024: View the current construction progress (as of September 7, 2024). The entire facility is nearing completion.

August 2024: See the current construction progress (as of August 1, 2024). The center purlin of the pump house has been installed.

July 2024: See the current construction progress (as of July 17, 2024). When building our hydroelectric power plants, it is particularly important to us to integrate the structures into the natural environment as seamlessly as possible.

May 2024: The photos show the progress of construction work on the pump house, the transfer station, the access road, and the current water flow. We plan to complete the entire facility by summer 2024.

February 2024: The photos show the progress of construction work on the pump house.

January 2024: Construction of the pump house foundation.

December 2023: Most of the construction work—including the construction of the power plant building, the laying of pipelines, and the water intake—is 70% complete. The turbines have already been delivered and are in storage on site.

September 2020 – Construction Begins on the Limone Hydroelectric Power Plant

Project Information

In Limone, in the province of Cuneo in Piedmont, the Ranft Group has initiated the construction of a new pressurized pipeline power plant and has already begun work on the project. The turbine has a rated capacity of 3,400 kW, which is expected to result in an average annual output of approximately 6,000,000 kWh. In the Francis turbine used here, water flows into the runner via adjustable guide vanes, allowing the output to be precisely controlled.

The photo on the left shows one of the three turbines for the Limone project, which are already at our depot in Ormea. The photo on the right shows the Vermenagna River a few kilometers downstream from the planned small-scale hydroelectric power plant. Even at this level—which is nearly the lowest of the year—the river carries a sufficient volume of water.

Key Data

  • Location:Italy, Piedmont
  • Capacity:6 million kWh per year

Hydropower's ability to provide baseload power makes it an attractive technology for the energy transition. If you'd like to learn more about our hydropower projects, click here.

Invest Wisely Now

If you, too, are interested in contributing to the energy transition while also benefiting from attractive interest rates, you’ll find helpful information on the “Invest” page .