Dear Investors,

The photovoltaic system in Wolfsloch is now feeding electricity into the grid; a battery storage system is also planned there. In Westeregeln, the building permit for the green electricity storage facility has been granted. For Neubrunn and Holzkirchen, there are new prospects for grid connection. In Aalen, we have aligned the planning for the solar park and storage facility with the available grid capacities.
In this report, we provide an update on these projects and the planned acquisition of additional project rights. We also share what Michael Ranft discussed with Anleihen-Finder and present

We sincerely thank you for your trust and hope you enjoy reading this.

Sincerely, Michael Ranft, Andrea Ranft, and Rainer Zepke

EEN PROJECTS IN GERMANY

Wolf's Den

The photovoltaic plant in Wolfsloch, with a capacity of approximately 8 MWp, has been feeding electricity into the public grid since June 1, 2026. The next step is the installation of a battery storage system, which is scheduled to go online in the second quarter of 2027. It is intended to temporarily store the generated electricity and enable more flexible grid injection and marketing. Marketing of the plant is also progressing: The 20 plant shares were firmly reserved within a short period of time. In the meantime, nearly all shares have been sold to investors.

Westeregeln

The photovoltaic plant in Westeregeln has been connected to the grid since January 15, 2026. For the supplementary green power storage facility, with a capacity of 2 MW and 4.5 MWh, both the grid connection approval and the building permit have now been granted. The storage facility is being offered to investors; implementation can then begin. For the separately planned gray electricity storage facility, there has been a positive response to the preliminary building permit application. However, according to the current project status, the grid access originally promised is no longer available. Therefore, a new grid access application to Avacon is planned for summer 2027. Whether and when the storage facility can be built depends on the outcome of that application.

Würburg County

A new connection option has been identified with the grid operator for the photovoltaic projects in Neubrunn and Holzkirchen, which together total approximately 46 MWp. The grid connection point originally planned is no longer available. Planning can now also proceed for the addition of battery storage to both projects. The grid connections are scheduled to be available in phases between late 2027 and 2031. Based on this, we can plan the cable routes and the remaining approval steps.

Aalen

For the Aalen project, we are planning a 10 MWp photovoltaic system and a battery storage system with 5 MW of power and 20 MWh of capacity. Together with Stadtwerke Aalen, we have adapted the system design to accommodate limited grid capacity: The planned grid connection is expected to range between 2.75 and 3.5 MW. The storage system helps feed solar power into the grid with greater flexibility and makes better use of the connection. We expect to receive the building permit by the end of October 2026; construction is still scheduled to begin in the fourth quarter.

Acquisition of Project Rights

In addition to our own project developments, we are evaluating the strategic acquisition of project rights that are at an advanced stage of development. This will enable us to bring additional photovoltaic systems—preferably equipped with battery storage—to fruition. We are currently conducting an exclusive review of three projects totaling approximately 50 MWp of photovoltaic capacity and green energy storage systems. Any acquisition is contingent upon a successful review of the projects.

MICHAEL RANFT IN AN INTERVIEW WITH ANLEIHENFINDER

How is the Ranft Group continuing to develop, and what role do battery storage systems play in this? In an interview with Anleihen Finder, founder and CEO Michael Ranft discusses the projects to be financed with proceeds from the Ranft Energie Bond 2026. He explains why early financing helps secure grid connections and move projects forward quickly. Another key focus is the integration of solar power and battery storage, which allows for more flexible electricity supply and better utilization of existing grid connections. Michael Ranft also explains why the group prioritizes feasible projects and sustainable financing in its pipeline. The interview thus provides insight into the Ranft Group’s next steps in Germany, Italy, and Austria. Click here for the interview

RANFT ENERGY BOND 2026

Invest in the energy of tomorrow
Generating solar power, storing energy, and making electricity available when it’s needed: The Ranft Group is working on this through projects in Germany, Italy, and Austria. With the Ranft Energy Bond 2026, investors can support this development. The corporate bond issued by Ranft Projekte 20 GmbH offers an annual interest rate of 7.00%, with interest paid semiannually on April 1 and October 1. The term ends on June 30, 2031; subscriptions are available starting at 3,000 euros. Redemption at 100% of face value is scheduled for July 1, 2031. For subscriptions made after the term begins, interest is calculated from the respective payment date.

If you would like to learn more about the bond, its opportunities, and its risks, you can find all the information and the option to subscribe on our bond page.