Dear Investors, the year is drawing to a close, and it’s hard to believe how quickly time flies. This makes it all the more gratifying that we can look back on a very successful year. Our success is based on our business model and the outstanding work of our dedicated team, as well as your investment in our forward-looking projects. This year, we were able to complete more than 30 MWp of photovoltaic projects and successfully develop and sell approximately 70 MWp. We are starting the coming year with an impressive project pipeline of 694 MWp, of which 96 MWp are expected to reach construction-ready status next year. With our growing team, we are optimistic about the implementation of these new projects and look forward to creating sustainable and meaningful projects together with you. In this Ranft Report 4/2024, we provide you with an overview of the Ranft Group’s current developments and projects in the renewable energy sector, as well as a summary of the 2024 fiscal year. Our ongoing investments, strategic partnerships, and use of state-of-the-art technologies have expanded our portfolio and further strengthened our market position. We are proud to make a significant contribution to the promotion of renewable energy while simultaneously generating attractive returns for our investors. The Ranft Group develops and implements projects in the photovoltaic sector in Germany, Italy, and Austria; in the hydropower sector in Italy; and in the large-scale energy storage (BESS) sector, initially in Italy. Are you already an investor with us? If so, we hope you’ll continue to support us. If you are not yet part of our investor community, we look forward to welcoming you in the future. Let’s continue to work together consistently over the coming years to create meaningful and value-adding projects.
Sincerely, Michael Ranft, Andrea Ranft, and Rainer Zepke
OPEN-SPACE SOLAR PROJECTS IN GERMANY
New Pirna 16.25 MWp Plant
Project Details: The ground-mounted PV plant in Pirna will have a total capacity of approximately 16.25 MWp. The minimum operating life of the ground-mounted PV plant is 30 years. The initial specific annual yield is 1,068 kWh/kWp, resulting in an annual electricity production of approximately 17 million kWh. Construction began as scheduled on August 1, 2024.
Location: The PV plant is located in the municipality of Pirna (state of Saxony, district of Saxon Switzerland-Eastern Ore Mountains). The grid connection point is the nearby substation in Heidenau. As of December 16, 2024 (image): The project continues to progress on schedule and will be technically operational and available to all investors as of December 31, 2024. The transformer stations have been delivered and have already been successfully installed. Both the module installation and the inverter installation will be completed by December 30, 2024. The construction of the transmission line to the substation and the installation of the transfer station in front of the substation will be completed this week.

New 22.4 MWp Kleinochsenfurt Plant
We are preparing the resolution for the Kleinochsenfurt solar park. Together with a long-standing partner, we are planning to build a substation for the plant; you’ll find more details in upcoming reports.
EEN PROJECTS IN ITALY
The Ranft Group Italy is celebrating a successful year, both in project development and in the completion of two hydroelectric power plants. The Ranft Group’s project pipeline in Italy includes photovoltaic projects with a total capacity of over 194 MWp.
Sale of Project Pipeline: 24 Million Euros
Over the past four years, we have brought a project development portfolio of approximately 66 MWp in Sicily to the construction stage
. We have now sold this portfolio to a strong partner for implementation. The Ranft Group will receive approximately 24 million EUR from this transaction. The proceeds from the sale of the aforementioned 66 MWp in project development will be recognized in the income from investments of the German subsidiaries, amounting to approximately 14 million EUR in the years 2024–2026.
Completion of the Codolo
Our Codolo hydroelectric power plant, with an annual output of approximately 2.4 million kWh, is now fully completed. Work is currently underway to prepare for commissioning.
Completion of the Limone
Project: Final work on the grid connection is underway in Limone. The project is scheduled for completion later this year. The plant will feed approximately 6 million kWh into the grid in the future. As was the case in Codolo, great care was taken during the construction of the hydroelectric power plant to ensure it blends in as seamlessly as possible with the natural surroundings.