The energy supply of the future requires more than just expansion: it calls for smart solutions that integrate generation, storage, and grid infrastructure. This is exactly where the Ranft Group comes in: We develop integrated energy parks that combine renewable energy production with modern storage technologies.
We are currently not only making progress in the construction of our solar power plants, but are also moving forward with the integration of large-scale storage systems and the conclusion of long-term power purchase agreements. In this way, we ensure that green electricity is not only produced, but also flexibly stored, marketed in a way that maximizes revenue, and reliably purchased through stable contracts.
In this issue of the Ranft Report 3/2025, you’ll find the latest updates on the construction progress of our facilities as well as on the planned integration of the storage systems. Together, we are shaping the next phase of the energy transition—in a sustainable, forward-looking, and investment-driven way.
EEN PROJECTS IN GERMANY
New Westeregeln Plant, 5.6 MWp
A lot has happened since the last newsletter. The DC side of the system is already complete. The installation of the AC cabling and the transformers is in full swing.

Construction is proceeding according to schedule, and we expect the plant to be connected to the grid in the fall of 2025. Once connected, the plant will feed approximately 6 million kWh into the grid each year, thereby reducing CO₂ emissions by approximately 4,400 metric tons annually. A large-scale storage facility is also planned for the plant. As a result, the plant will make a significant contribution to the region’s green energy supply.

Current Projects in the Approval Process
In Kleinochsenfurt, we have received the resolution on the bylaws from the city of Ochsenfurt. The zoning plan is currently awaiting approval from the relevant authority. A capacity of 22 MW is planned for this project.
In Willingsheim, grid connection approval has now been granted for the planned 3 MW green energy storage facility. At the same time, the 3 MWp photovoltaic plant is currently undergoing the zoning plan process. The first round of design considerations is currently underway.
In Aalen, the second round of public consultation is currently underway. In the next step, the municipality and the relevant authority will prepare the resolution to amend the zoning ordinance. The plan here is to build a 10 MW photovoltaic plant.
BESS Projects in Westeregeln, Pirna, and Oranienbaum
The Ranft Group is not only driving the expansion of photovoltaics in Germany but is also strategically supplementing its existing solar parks with high-performance large-scale storage solutions (Battery Energy Storage Systems, BESS). Specifically, storage systems are being installed at the Westeregeln (6 MW), Pirna (16 MW), and Oranienbaum (6 MW) sites, which will be directly connected to the ground-mounted PV systems there.

The integration of storage systems is a crucial step toward further increasing the economic viability and systemic importance of our projects. By their very nature, photovoltaic systems generate electricity depending on the time of day and weather conditions. Energy storage systems balance out these fluctuations by temporarily storing excess solar power and feeding it back into the grid at a later time—particularly during periods of high demand and higher market prices. This not only strengthens the security of supply but also enables revenue optimization in electricity trading.
For investors, this means added value:
- Flexibility: The green electricity generated can be sold on the market at the most opportune times.
- Increased Revenue: Electricity is not only produced but also traded strategically—this can significantly boost revenue.
- System Benefits: Storage systems make an important contribution to grid stability and increase acceptance of large-scale PV plants.
- Future-readiness: By combining PV and energy storage, the Ranft Group is positioning itself early on in a market segment that is of central importance to the energy transition.
The Westeregeln, Pirna, and Oranienbaum projects are thus not merely traditional PV power plants, but are evolving into integrated energy parks that offer a sustainable and economically attractive outlook for the coming years.
RANFT ENERGY BOND 2025
Analysis by Philipp Nerb: In his latest analysis, financial expert Philipp Nerb rates the Ranft Solar 2025 bond as “very good” (1-). He particularly highlights the Ranft Group’s long-standing track record of success,
the high degree of planning certainty in the target market, as well as the bond’s conservative yet innovative structure. You can find Mr. Nerb’s full analysis here: https://www.finanzwelt.de/post/werteanalyse-ranft-solar-anleihe-2025