Project News

Here you'll always find the latest project-related news and can easily track the project's progress.

December 2025: Since the last report, work on the Westeregeln photovoltaic park has continued successfully and proceeded according to plan. Following the installation of the fencing, the completion of the foundation work, the full construction of the substructure, and the extensive module installation, the modules have been fully wired to the inverters, making the system technically operational. The transformers and transfer stations required for grid connection have been delivered, installed, and electrically connected to the PV systems. The plant certificate has been issued and is now available. The grid operator is currently working on the connection from the transfer station to the grid interconnection point. The date for the actual connection of the entire PV park to the public power grid by the responsible grid operator, Avacon, has not yet been announced.

October 2025: Following the installation of the fence, the completion of the foundation work, the full construction of the substructure, and the extensive module installation, the modules have been fully wired to the inverters, making the system technically ready for operation.

The transformers and transfer stations required for grid connection have been delivered, installed, and electrically connected to the PV systems. The system certificate has been issued and will be sent to us within the next two weeks.

The short connection from the transfer station to the grid interconnection point, as well as the actual connection of the entire PV park for feed-in, is now the responsibility of the relevant grid operator, Avacon. This means that the technical requirements for future feed-in operations have been met.

August 2025: Three inverters with a total capacity of approximately 1 MW have been installed, cable trays have been laid, and the DC cables have been successfully routed to and connected to the inverters.
The foundation work for the remaining substructure has now been completed. This also allowed the rack construction to be fully completed. At the same time, module installation work has continued according to schedule. Rows 1–13 in the southwestern section and rows 2–8 in the southeastern section have now been installed. In addition, the foundation tray and the transformer have been delivered and installed, marking another crucial step toward grid connection.

July 2025: The photovoltaic project in Saxony-Anhalt, with a capacity of approximately 5.6 MWp, is progressing as planned. Preparatory work on the site of a former industrial brownfield has been successfully completed. To protect the construction materials, the entire fence system surrounding the project site has already been fully erected.

Construction work on the substructure, including the load-bearing foundations, has progressed further. Work is moving particularly quickly in the southern section of the facility: Here, the substructure has already been fully erected, the first module tables have been installed, and photovoltaic modules have been mounted on them.

Over the coming weeks, work on the substructure will continue steadily. At the same time, the modules will be installed in stages. We have been informed that the target delivery date for the transfer station is August 2025. We are currently in communication with the grid operator regarding the connection to the public power grid.

June 2025: The approximately 5.6 MWp PV project in Saxony-Anhalt is progressing as planned: Preparations are underway on the site of a former industrial brownfield.

A fence is currently being erected around the construction site to ensure the safety of the building materials. Construction is being carried out using a load-bearing foundation, which eliminates the need for earthwork—a proven and sustainable method that is particularly well-suited to the on-site conditions. In the coming weeks , we will begin assembling the substructure and gradually installing the modules. We have thus successfully reached the first milestones on the path to commissioning.

Project Background

The solar park is being built on a former industrial brownfield site in the municipality of Westeregeln, Saxony-Anhalt (Salzlandkreis district). The site was leveled in advance for construction and will be built using a ballast foundation system, which eliminates the need for any interference with the soil structure. Electricity is fed into the grid via the grid connection point located near the property.

Project Information

The ground-mounted PV plant in Westeregeln has a planned total capacity of approximately 5.6 MWp. The PV plant is projected to generate a total of approximately 6 million kWh of electricity annually.  This amount of electricity generated can supply 2,000 households—each with an average annual consumption of 3,000 kWh—with green electricity. In addition, we will achieve an annual CO2 reduction of 4,144 metric tons. Construction began as scheduled in February 2025.

Key Data

  • State:Saxony-Anhalt
  • Capacity:5.6 MWp
  • Modules:–
  • Inverter:–