December 2024: The Riedenheim ground-mounted solar power plant was successfully completed
August 2024: Here you can see the construction progress of the Riedenheim ground-mounted solar power plant (as of August 1, 2024). The plant is nearing completion. The following work has been completed so far:
- All modules have been installed
- All strings are connected to each other
- Inverters were installed and strings were connected
- The fence with a gate has been completed
The stations are currently being completed.

July 2024: Here you can see the construction progress of the Riedenheim ground-mounted solar power plant (as of July 17, 2024). Construction of the plant is proceeding according to plan.

May 2024: Here you can see the construction progress of the Riedenheim ground-mounted solar power plant (as of May 29, 2024)s

May 2024: Construction begins on the ground-mounted solar power plant with a capacity of approximately 10 MWp.

Project Information
For the ground-mounted solar power plant in Riedenheim, with a capacity of approximately 10 MWp, we received final approval from the municipality of Riedenheim in July 2023 and a building permit from the Würzburg District Office in November 2023.
Key Data
- State:Bavaria
- Capacity:10 MWp
- Modules:Longi HTD 580W by Longi
- Inverter:SUN2000-330KTL-H1 by Huawei