May 2025: The final safety inspection of the transfer station for the meter installation has now been completed, as has the completion and commissioning of the transfer station.
We are currently carrying out the final parameterization work to optimize the system.
The expert inspection of the PV system by a certified inspector from the German Solar Energy Society, Berlin-Brandenburg Regional Association (DGS), took place as planned on April 10, 2025. The inspection was successful, and the minor issues identified will be resolved promptly. Grid connection will take place on May 1, 2025. The Pirna PV project will feed approximately 17 million kWh into the grid annually, thereby saving 12,500 metric tons of CO₂ each year.

January 2025: The civil engineering work, including the complete installation of cables from the transfer station to the substation, was successfully completed. The transfer station will be connected to the substation in mid-February. Afterward, the protective testing will be carried out using the cable testing vehicle. Commissioning of the entire facility is scheduled for the second half of February.

December 2024: The Pirna project is in its final phase. Module installation will be completed before Christmas; all inverters have been fully installed; the DC cabling is complete; and the system is now technically ready for operation. Construction of the cable route to the substation is 90% complete, so cable laying will also be finished by the end of the year. The transfer station was delivered and installed today. Commissioning is scheduled for the first quarter of 2025.

November 2024: The project continues to make progress, and key milestones have already been reached. The substations have been delivered and successfully installed. At the same time, module installation is underway. Work on the inverters is proceeding according to plan, and half of them have already been installed. At the same time, construction of the transmission line is moving forward to feed electricity into the designated substation in the future. Furthermore, the excavation for the transfer station has been completed; the station itself will be delivered and installed in the next phase.

October 2024: In October, the transformer basins for the two planned transformer stations were successfully installed. Construction of the module table substructures for the east and west orientations is now in full swing, and the first elements are already complete. Full construction will take place after the southern module tables have been installed. This is in accordance with the optimized construction schedule. Furthermore, the modules are being delivered and assembled on a weekly basis. The flood protection wall has been completed and now provides reliable protection. The cables from the inverters to the transformer stations have also been laid. This means that the inverters, which have now been fully delivered, can be installed and connected as the modules are installed.

September 2024: The substructure of the ground-mounted PV system is nearing completion; the module racks facing east and west are still being installed. More than 1,000 modules have already been installed. The flood protection wall is also nearly complete. In addition, trenches have been dug for the AC cabling from the inverters to the substations.

The complex can be divided into two sections, which we will refer to in the following text as “Park West” and “Park East.”

Park West: The cable trenches have been completed. This means that the inverter cables have been laid and the trenches have since been filled in.

Park East: The cable trenches for the inverter cables have been dug. According to the schedule, the cables will be laid in calendar week 42.

Further planning for the entire park in calendar week 41: The AC cables from the inverters to the transformer stations are to be laid, and the foundation trench for the transformer station will be delivered.

August 2024: Construction began as planned on August 1. The photo documentation shows the progress made so far. Work is currently underway on the substructure and the flood protection wall. We will continue to provide monthly updates on the progress of the Pirna ground-mounted solar power plant.

Project Information

Project Details: The ground-mounted PV system in Pirna will have a total capacity of approximately 16.25 MWp. The minimum operating life of the ground-mounted photovoltaic plant is 30 years. The average annual yield is 1,068 kWh/kWp, resulting in an annual electricity production of approximately 17 million kWh. Construction began as scheduled on August 1, 2024.

Location: The solar power plant is located in the municipality of Pirna (state of Saxony, district of Saxon Switzerland-Eastern Ore Mountains). The grid connection point is the nearby substation in Heidenau. The total area of the property is approximately 170,000 square meters, of which about 130,000 square meters are used for the solar power plant.

Key Data

  • State:Saxony
  • Capacity:16.25 MWp
  • Modules:Tenka Solar – Orion Series IX Bifacial 700-watt
  • Inverter:SUN 2000-330 KTL by Huawei