Project News

Here you'll always find the latest project-related news and can easily track the project's progress.

December 2023: Completion of the 5 MWp ground-mounted solar power plant

November 2023: Start of construction on the ground-mounted solar power plant

October 2023: The steps in the zoning plan process were completed, and a building permit was applied for.

Aerial view of the construction site in Obergessertshausen

Project Background

To help drive the energy transition in Germany, the Ranft Group is building a 5 MWp ground-mounted solar farm in Obergessertshausen (Bavaria). The site is also planned to be used for sheep grazing, which offers several advantages:

  • The simplest and usually most cost-effective care option
  • Environmentally friendly, gentle maintenance of the areas.
  • Unlike mechanical mowing, there is no risk of dust formation or damage to the panels from stone chips.
  • Regular patrols by the shepherd on the premises at irregular intervals significantly reduce the risk of theft and vandalism.
  • Visible damage can be repaired more quickly thanks to the shepherd's inspection
  • Grazing can reduce the number of mouse tunnels and molehills on the grounds.
  • The use of natural sheep grazing as a land management practice is compatible with ecological electricity generation and enjoys a high level of public acceptance.

Project Information

The Ranft Group is building a 5 MWp ground-mounted solar power plant in Obergessertshausen.

Key Data

  • State:Bavaria
  • Capacity:5 MWp
  • Modules:Longhi LR5-72-HBD 550 Modules
  • Inverter:Huawei Sun 2000 215 KTL