Project News

Here you'll always find the latest project-related news and can easily track the project's progress.

December 2021: Completion of the first construction phase of the option site with approximately 3.8 MWp.

November 2021: The system has been commissioned under the EEG.

September 2021: The project site, with a nominal capacity of approximately 5 MW, is to be developed in two phases. Construction of the second phase is scheduled for 2022–2023. We have received the building permit for the first phase, and work is already in full swing. The plant will be connected to the grid in December 2021 as part of the first construction phase. The plant is part of a Power-to-X project.

May 7, 2021 – The 9.25 MW solar power plant was commissioned on May 7, 2021. The plant was also connected to the grid on that date. We are very pleased that the plant is now feeding electricity into the public grid. We would like to thank Project Manager Stefan Hauf and our team for the successful implementation of this project.

Solar Power System in Bad Langensalza

April 2021: All work is on schedule. Fire department access road completed, drainage trough completed, medium-voltage system,
transformer stations and transfer station completed, communication lines laid, fencing approximately 90% complete, 100% of modules delivered, 50% of modules installed, all inverters mounted, electricity meter installed
EEG commissioning scheduled for May 7, 2021

March 2021: All work in Bad Langensalza is on schedule. You can see the current construction progress in the aerial view. (Drainage basin complete, medium-voltage system complete, transformer stations and transfer station complete, communication lines laid, fencing approximately 90% complete, 38% of modules delivered and installed)
EEG commissioning scheduled for May 7, 2021

February 2021: All work in Bad Langensalza is on schedule. You can see the current construction progress in the aerial photo. (Fire department access road completed; the main medium-voltage trench is currently being backfilled; medium-voltage lines are being laid; communication lines are being laid; approximately 65% of the fence has been driven into the ground; the locations of the module tables have been staked out)

January 2021: Start of construction

Jan. 15, 2020 – Special Bidding Process: Contract Awarded for Photovoltaic Project

Project Background

Decarbonization, Decentralization, and Digitalization

The project focuses on replacing centralized fossil-fuel-based power generation with decentralized renewable power generation.

To bridge the “dark lull” typical of photovoltaic systems and to enable the temporary storage of electricity, the park is being equipped with an innovative energy storage system from JenaBatteries GmbH. The metal-free redox flow battery serves as a new pillar of the energy system.

The facility plays a role in the energy transition through intelligent systems that use big data and digitalization concepts to balance production and consumption.

Building Lot in Bad Langensalza

Project Information

We waited six weeks for the Federal Network Agency to announce the results of the special tender for photovoltaic systems. Now, as part of the special tender process, we were awarded the contract for the photovoltaic project in Bad Langensalza on January 15, 2020.

The project is a south-facing ground-mounted solar farm covering an area of approximately 10 ha. The planned rated capacity of the plant is 9.25 MWp. An investment of approximately 6 million euros is estimated for the construction of the ground-mounted solar farm. The project in Bad Langensalza is part of a model and showcase project that will also incorporate other future technologies, such as a Power-to-X facility. Power-to-X refers to the storage or other utilization of surplus electricity. This allows the generated electricity to be used, for example, to produce hydrogen. The integration of a large-scale storage system from our subsidiaryJena Batteriesis also planned.

We are very pleased to contribute to the energy transition with yet another climate-friendly project, so that we can help shape a more environmentally friendly future.

Furthermore, the project represents another important milestone for our company and thus marks a successful start to 2020!

Key Data

  • State:Thuringia
  • Capacity:9.25 MWp
  • Modules:to be determined
  • Inverter:to be determined

Invest Wisely Now

If you, too, are interested in contributing to the energy transition while also benefiting from attractive interest rates, you’ll find helpful information on the “Invest” page .

The owner of this website is committed to accessibility and inclusion. Please report any issues you encounter using the contact form on this website. This site uses the WP ADA Compliance Check plugin to improve accessibility.