In this report, we discuss these projects and the planned acquisition of additional project rights. We also share what Michael Ranft discussed with Anleihen-Finder and present
Dear Investors, It’s hard to believe, but the first half of 2026 is already behind us. The past few months have been marked by numerous advances for the Ranft Group in Germany, Italy, and Austria. We were able to further expand our activities, particularly in the area of battery storage.
Westeregeln Green Energy Storage Facility – A positive grid assessment has already been received for the planned battery storage facility (2 MW capacity, 4.5 MWh storage capacity). The […]
Together with a project partner, the Ranft Group is building a solar power plant with a green energy storage system in Wolfsloch near Helmstadt-Bargen in Baden-Württemberg. The solar power plant […]
The Ranft Group has reached another important milestone in its international project business: The Serragarafalo solar project in Sicily has been successfully sold.
For the Ranft Group, the 2025 fiscal year was marked by growth, consolidation, and strategic development. In Germany, Austria, and Italy, numerous projects were successfully implemented or made significant progress.
December 2025: Since the last report, work on the Westeregeln photovoltaic park has continued successfully and proceeded according to plan. Following the installation of the fencing, the completion of the foundation work, the full construction of the substructure, and the extensive module installation, the modules have been fully wired to the inverters, making the plant technically ready for operation.
The energy supply of the future requires more than just expansion: it calls for smart solutions that integrate generation, storage, and grid infrastructure. This is exactly where the Ranft Group comes in: We develop integrated energy parks that combine renewable energy production with modern storage technologies.
The energy sector operates in a dynamic environment and faces a number of challenges. As European electricity demand continues to rise, renewable energy is rapidly gaining in importance—not only as a climate-friendly alternative, but also as a cornerstone of security of supply, economic resilience, and geopolitical independence.
May 2025: The final safety inspection of the transfer station for meter installation has now been completed, as have the completion and commissioning of the transfer station. We are currently carrying out the final parameterization work to optimize the system.